Delray Beach Master Plan Phase 2 Nighttime Pavement Stamping

Post Date:11/05/2019 10:01 AM

Please be advised of multiple temporary lane closures for asphalt brick stamping occurring nightly between Nov. 5, 2019 - Nov. 15, 2019 along A1A. There will be workers in the roadway directing traffic. The stamping of the asphalt is dependent on the weather. Any change in the schedule will be posted as soon as possible. 

Time: 9 PM - 7 AM

Date: Nov. 5 - Nov. 9

Location:

  • Intersection of Atlantic Ave. & A1A and the Marriott Crosswalk
  • Intersection of Casuarina Rd. & A1A and the Anchor Park Crosswalk

Night work for asphalt brick stamping and painting is set to begin at 9 PM, Tuesday (Nov. 5) to 7 AM Wednesday (Nov. 6, 209). Temporary lanes closures will be set up with workers in place for traffic control.

The work sequence for the week is as follows:

  • Nov. 5, Tuesday night to Nov. 6, Wednesday morning  - The intersection of Atlantic Ave. & A1A and the Marriott Crosswalk. 
  • Nov. 6, Wednesday night to Nov. 7, Thursday morning – The intersection of Atlantic Ave. & A1A and the Marriott Crosswalk. 
  • Nov. 7, Thursday night  to Nov. 8, Friday morning- The intersection of Casuarina Rd. & A1A and the Anchor Park Crosswalk. 
  • Nov. 8, Friday night to Nov. 9, Saturday morning – The intersection of Casuarina Rd. & A1A and the Anchor Park Crosswalk. 

 


 

Time: 12 AM- 8AM

Date: Nov. 11 - Nov. 13

Location:

  • Intersection of Atlantic Ave. and Gleason St.
  • Intersection of Atlantic Ave & Venetian Dr.

The next phase of night work for asphalt brick stamping and painting is set to begin at 12 AM Monday (Nov. 11) to 8 AM, Tuesday (Nov. 12) and conclude at 8 AM, Wednesday (Nov. 13). Temporary lanes closures will be set up with workers in place for traffic control.

  • Intersections of Atlantic Ave & Gleason St and also Atlantic Ave & Venetian Dr.
  • Work will begin at 12 AM through 8 AM for these intersections.
  • The work will be completed over 3 days.
  • Temporary lane closures will be set up but there will always remain two-way traffic during the lane closures. 

 


 

Time: 9 PM- 7 AM

Date: Nov. 14 - Nov. 15

Location: 

  • Sandoway Center Crosswalk along A1A
  • Intersection of Thomas St. and A1A
  • Intersection of Beach Dr. and A1A
  • Crosswalk between Crestwood Dr. and Beach Dr. along A1A

The last phase of night work for asphalt brick stamping and painting is set to begin at 9 PM Thursday (Nov. 14, 2019) and conclude at 7 AM, Friday (Nov. 15). The remaining crosswalks along A1A will be completed. These include the crosswalks at Sandoway Center, Thomas St., and Beach Dr.. Temporary Lanes closures will be set up with workers for in place for traffic control.

 

 