Road Closure info for Block 63 and Block 17 Alleys Project

Post Date:07/11/2019 3:49 PM

Important Road Closure Info

Please be advised Public works is going to start construction on two alleys July 15, Please see the information below for the Alleys, and also attached information. 


Date

Construction begins on July 15, 2019 and the project duration will be 90 days. 

Locations

Block 63 Alley

  • Limits are SW 3rd St. and SW 2nd ST and SW 1st Ave and S Swinton Ave

Block 17 Alley

  • Limits are NW 3rd St and NW 4th ST and NW 5th Ave and NW 6th  Ave

Project Information

The Contractor has provided an approved Traffic Control Plan for this project. The Contractor will be detouring Non-Local Traffic outside of the Alleys and Specific Intersections during phases of the work. The contractor is required to provide local access to your property throughout the duration of the project

 